Metcalf Avenue Improvements

99th Street to 103rd Street

Client: City of Overland Park, Kansas

This project will widen this section of Metcalf Avenue from four lanes to six lanes, adding capacity by matching the six-lane sections already in place both north and south of the project.  A large portion of the project will improve storm drainage.  Our design includes replacing two bridges over Indian Creek, adding inlets and pipes along the roadway, extending the existing 25-foot by 16-foot RCB, installing a 36-foot by 10-foot Conspan on a side street and bank stabilization.

SIGNIFICANT DESIGN ITEMS:

  • Bridge design
  • RCB extension
  • Conspan structure
  • Channel/bank stabilization
  • Drainage improvements
  • Permitting
  • Property descriptions
  • Public involvement
  • Utility coordination
  • Erosion control

COMPLETION DATE: 2008

COST: $8 MILLION

PROJECT PHOTOS (Click to enlarge)