Affinis engineers provided design services to upgrade 12 blocks of residential streets in Old Town Lenexa. The project converted open-ditch-section streets to curb and gutter streets with new enclosed storm drainage systems. Construction was completed in 2003.

SIGNIFICANT DESIGN ITEMS:

  • Legal descriptions
  • Construction phasing
  • Public involvement
  • Utility coordination
  • On-street parking provisions
  • Storm sewers

COMPLETION DATE: 2003

COST: $600,000